The first step of investment:
plot
choosing
Fengpu Industrial Park provides land with complete layout and infrastructure and various standard workshop for our clients. |
The second step of investment: constract signing After the plot or workshop is chosen, client will sign the investment agreement with Shanghai Fengpu Industrial Park, guaranteeing the mutual rights and obligation . Clients who purchases the land will sign the Land Use Right Grant Contract with the Shanghai Fengxian District Housing and Land Administration Bureau. |
The third step of investment: project approval and registration
 |
The fourth step of invetment: project examination and approval |
| |
|
Information provided by clients |
Examination and transaction term |
Text grant |
Grant fee come to hand |
|
First step |
Plot choosing and project examination |
1. title of clients' company 2. letter of intent of the plot location 3. land area
|
3 days |
the suggestion from engineering department |
|
|
Second step |
Project establishment |
feasibility study report |
8 days |
the authorization from project department |
|
|
Third step |
Plot choosing |
1. project commission approval 2. plane layout 3. seal of the plot application form 4. relief map in 4 originals 5. pay relative fees
|
10 days |
the permission of construction land using |
|
|
Fourth step |
Land levy of the project |
1.
plot choosing
2. plane layout 3. seal the land application form
|
7 days |
the test report by land department |
|
|
Fifth step |
Report to superior authority for examination and approval |
Report to the superior authority by the Fengxian Housing and Land Administration Bureau |
1-2 months |
the authorization from land department |
|
|
Sixth step |
Construction licence examination and approval |
1. land use right approval 2. relief map in 3 originals 3. shop drawing in 4 originals 4. fire protection examination and approval 5. sanitation and environment protection 6. greenbelt design examination 7. pay commission charge
|
10 days |
the permission of construction project |
|
|
Seventh step |
Transact Land use right ceritificate |
1. land use right approval 2. business licence 3. corporation code certificate
|
10 days |
the certification of land property |
| |
Fifth step: workshop construction First,preliminary work of the project Assist to handling the following relevant procedures of the project 1, fulfill the site cleaning and leveing 2, recommendate the realization of the geological prospecting work 3, recommendate and deside the design institute to design 4, organize and arrange the examination and approval of the first design scheme 5, receice the approval from the project committee, planning bureau and the land bureau,etc. 6, carry out the examination and aproval from the fire prevention, environmental protection, health, guard department 7, prvide the temporary water and electricity
Second, related project service content 1, recommendat the construction bidding unit 2, arrange and decide related construction bidding 3, applicate the construction license and handle the reporting and supervising procedure 4, applicate the formal water and electricity 5, assist the clients to deal with the construction schedule and quality etc. 6, organize and arrange the check and acceptance of the project in every phase 7, recommendate and carry out and participate the project final accounts audit with the audit unit 8, hand over the project when it finished |
put into production
| |
 |